Glenfarne requests more time to build Magnolia LNG

Rate this article

By Adnan Bajic Units of Glenfarne Group and Kinder Morgan have filed a request with the regulator seeking an extension for the Magnolia LNG project development.

Courtesy of LNG Limited

In its filing to the Federal Energy Regulatory Commission, Magnolia LNG and Kinder Morgan Louisiana Pipeline jointly requested an additional five year to place respective facilities into service.

To remind, Magnolia LNG, acquired by Glenfarne earlier this year, is an 8.8 million tonnes per annum (mtpa) LNG export project that has completed the FERC permitting process.

The Kinder Morgan Louisiana Pipeline will deliver 1.4 billion cubic feet per day of natural gas to the LNG project.

Read Full Article Here

For more great articles: LNG World News